Airline Operations: Nobody Owns the Delay: What a Catering Truck Taught Me About Fixing Airlines
As a former Airline Base Manager ,how I solved a recurring departure delay issue with just a 15 minute meeting, plus why you should apply Agile principles in all areas.
Same flight leaving 35 mins late 3 times in the space of a week. Ask the Ramp team, and they will say catering wasn’t there. Ask catering and they will tell you they were waiting on the gate to confirm. Ask the gate and they will say they’re still getting the inbound sorted.
They are all giving truthful answers.
As Base Manager it fell on my desk as part of the OTP(On-Time Performance) committee. We had processes to put in place. We created reports, had OTP meetings and lots of energy was spent finding out who was at fault. However, the issue re occurred.
A very short meeting
In the end, I decided to try a very short meeting. I had 1 person (Gate, Ramp, Catering) come in for our regular OTP meeting and spend 15 minutes with me. I didn’t ask for opinions, I gave them a paper with details of the last 10 delayed departures. We reviewed each one and noted the time:
Inbound landed
Catering Ordered
Catering Truck Arrival
Loading Completed
Boarding Started
We noticed 7 of the delays had the same issue.
Catering wasn’t being confirmed quickly enough. Some were confirmed after the boarding time had been set. This wasn’t actually catering being late, it was just no set point where everyone would say “we’re ready”. The gate had no idea when they would get info, the caterers didn’t know when to confirm, and the ramp were trying to do a quick turnaround but only had half of the picture.
Once we identified the issue, we could see it wasn’t “who caused this”, it was “what can we change together so it stops?” This was the real solution. Everything else was just faff.
A very boring solution
We simply had one rule. Try to confirm catering at least 20mins before your required boarding time. This wasn’t to get people boarding quicker, it was so the gate and ramp had the info they needed.
We put a simple visual board in place identifying when catering was ordered, dispatched, completed and confirmed. We had a daily huddle on the flights we were at risk of. We did this all as a 2 week sprint.
For the first few days it was a bit of a mess. We still had some phone confirms and some missing updates. People were still running into inbound delays and the plan was always changing. We took this as information and used our short review meetings to adjust.
By week 2 we had the gate knowing when catering was ready, the caterers knew when to confirm and the ramp had early identification. We proved it worked and added it to our station’s approved processes.
I’m not going to tell you a percentage but the delays no longer fell under “catering” or “gate”, they became ours. This is a big change!
Yes, this was Agile. No, we don’t need a consultant to tell us that.
You’re probably rolling your eyes. Most companies use Agile and it’s all Stand Up meetings and sticky notes. Nothing really changes!
I understand, but in my book " The Agile transformation of Airlines" is about getting issues identified quicker, solving them together and ensuring they work.
One thing will always remain the same. Checklists, approved maintenance task cards. Safety processes, regulations and your Safety Management System won’t be “iterated.” Agile should be applied to how you make improvements within your airline but never to any safety critical process. If something goes against a process, the process will always win.
4 examples of this outside the station
This pattern keeps coming up across other departments. Here are 4 examples:
Cabin Crew. Crew will do 4 sectors in a day, meaning they are dealing with hundreds of passengers. Usually you’ll have one debrief at the very end when everyone is tired and it’s too late. Alternatively, you can have a quick 2-3 minute huddle after every sector. You’ll identify issues, resolve any shortages and complaints before the next sector.
Engineering. Your backlog will be prioritized according to airworthiness, safety and operational impact. You’ll have this on a visible Kanban board. You’ll have a retrospective to identify any recurring defects and document issues. Planning will change but the actual maintenance won’t. Certifying staff have the authority.
HR. I’m biased but it’s all I know! You’ll have a hiring Kanban (Requisition, Sourcing, Screening, Interview, Offer, Joined) so you can see exactly where your candidates are getting held up. The first 30-90 days is really important as new starters will decide if they want to stay. Treat them like this.
Catering. Short feedback loops on your menu and production schedules will help reduce waste and respond to demand quicker.
Summer Airports = Chaos
Remember 2022? Demand returned faster than anyone expected. Thousands of staff had been let go during Covid so we had long security lines, lost baggage and lots of cancellations. Heathrow asked airlines to limit the number of passengers departing per day to around 100,000. Schiphol did something similar.
It’s frustrating that we had indicators that things were going to go wrong. We had long lines, baggage mishandling and no-shows. However we had planned our staffing based on seasonal forecasts but our demand was changing every week. Every party (airlines, airports, ground handlers, security) were optimizing their part of the process so no one had ownership of the whole passenger journey.
Agile wouldn’t have made us conjure up more staff. We can’t and background checks take ages! However we would have had a weekly forecasting cell, cross trained teams who can move to where the queue is, a live dashboard and small schedule reductions early on. Cancellations are still cancellations but they’re much kinder to passengers.
Would Agile save a failing airline?
No. I hate business speak so I’ll be straight with you.
An airline in India stopped flying in 2019 due to large debts, high cost base and governance issues. These are all issues at a board level and can’t be solved with a sprint. However they had clear indicators that they were struggling (yields decreasing, debt increasing, returning aircraft to lessors). They were also making decisions slowly. Teams were siloed and not looking at the same stats at a route level. These were the writings on the wall. Agile could have helped identify the issues quicker and give everyone more time (including staff and lenders). This is a real benefit!
The people factor
Airlines are full of clever, tired and proud people. From my experience if your employees don’t think management will listen then they’ll move on. Often this is now done via social media. This isn’t a campaign. It’s having regular conversations, treating complaints fairly and having leaders at pre-flight and shift briefings.
Younger generations like to have clear feedback and feel they’re being asked for their opinions. Treat them as an idea generator.
Only do one thing
Start with something small. Find one visual and winnable issue (like my catering issue) and bring the right 3/4 people together with real data. Do this as an experiment for 2 weeks. If it works then make it standard. If it doesn’t then you’ve lost 2 weeks but you’ve learnt something.
Don’t shout about it being a transformation across the airline. Let the results speak for themselves.